• Subtopic: Project Activities and Timelines | Actividad | Predecesor | Tiempos (días) | Rspta a) | | | | | |------------|------------|----------------|-----------|--|--|--|--| | | | Optimista | Probable | Pesimista | Tiempo Medio | Varianza | | A | - | 5 | 6 | 7 | 6 | 0.11 | | B | - | 4 | 5 | 18 | 7 | 5.44 | | C | A | 4 | 15 | 20 | 14 | 7.11 | | D | B, C | 3 | 4 | 5 | 4 | 0.11 | | E | A | 7 | 16 | 19 | 15 | 4.00 | This table summarizes the activities involved in the project, their predecessors, and the estimated durations based on optimistic, probable, and pessimistic scenarios. The "Tiempo Medio" (average time) and variance are also provided to assist in project planning and risk assessment.